Louisville High School Innovation Laboratory
Total Project Cost: $600,000 Actual Construction Cost: $500,000 Construction Timeline: 7/1/2019 to 5/29/2020
Society Devoted to the Sacred Heart Library Archive
Total Project Cost: $1,450,000 Actual Construction Cost: $1, 399,400 Construction Timeline: 10/28/2017 to 9/28/2018
St. Lawrence Martyr Parish Renovation
Total Project Cost: $2,165,000 Actual Construction Cost: $1,927,400 Construction Timeline: 6/6/2019 to 3/17/2020
Sagrado Corazon y Santa Maria de Guadalupe Parish
Total Project Cost: $4,000,000 Actual Construction Cost: $4,881,900 Construction Timeline: 1/1/2017 to 6/1/2018